$900 million for Blind Faith Field
12 Oct 2005
Blind Faith is located in approximately 7,000 feet of water, about 160 miles southeast of New Orleans, on Mississippi Canyon blocks 695 and 696. The discovery well was drilled in June 2001 and encountered more than 200 feet of net pay in Miocene sands at depths of 20,900 feet to 24,300 feet. A successful appraisal well was drilled in 2004. The field has an estimated gross resource potential exceeding 100 million barrels of oil-equivalent.
Total capital costs for the project will be approximately $900 million. Chevron's partner in the Blind Faith project is Kerr-McGee Corp., which holds a 37.5 percent interest.
Initial production is expected to be approximately 30,000 barrels of oil per day (b/d) and 30 million cubic feet of gas per day (mmcf/d). The semisubmersible facility will have a production capacity of approximately 45,000 b/d and 45 mmcf/d. The topsides can be upgraded to a capacity of 60,000 b/d and 150 mmcf/d to accommodate production from satellite discoveries or third-party tiebacks.