Testing time pays off for power plant project
10 Sep 2020
Collaboration and trust between two firms ensured careful research and testing to ensure a ground-breaking power plant worked to optimum efficiency...
There’s nothing ordinary about Arjun Infrastructures’ remarkable power plant in London, which generates 17MW of renewable energy from food waste and can also utilise fats, oils and greases (FOG).
The power plant sees 75GWh of the electricity sold to Thames Water for its Beckton sewerage processing plant (home to 64 Börger pumps), with the remaining 55GWh is purchased by Centrica.
Heat from the engine is supplied to the adjacent gas pressure reduction station owned by Cadent whilst heat recovery cycles of the CHiP technology increase the thermal efficiency of the Arjun plant.
”This is a first-of-a-kind plant. Joining up assets that haven’t previously been linked together before has presented many engineering challenges,” said Phil Jones, director at 2OC, who developed the plant and now manage it on behalf of Arjun.
Originally specified by Jacobs Engineering, the two 90kW lubrication pumps for the Combined Heat and intelligent Power (CHiP) plant had to be installed by main contractor J. Murphy and Sons in a very tight space.
David Brown,of Börger, manufacturer of the pumps, explained: “The small footprint was just one of many hurdles to negotiate – not to mention the fact that the pumps had to go below ground, beneath the plant’s engine”.
He added: “We designed a special base frame so that the very robust EL1550 Classic pumps could be mounted vertically into the small footprint (just 3m by 4m) – and then for easy servicing, lifted out and put on their side. Over-pressure protection was required too. All a bit tricky, but often the case when there’s not much space available.“
Testing times
Producing enough energy for approximately 40,000 homes, Arjun’s power station presents no shortage of high temperatures for its assets to cope with. This includes the Börger pumps, which had special cooling radiators for the gearboxes and motors installed.
Added Jones: “We had to meet the deadline for all-important government ROCs (Renewables Obligation Certificates) that support large-scale renewable electricity projects in the UK. To get the plant off on the right operational and financial footing, we had to make things happen to hit that deadline.”*
The construction contractors’ engineers were initially concerned about the noise and vibration of the two Börger pumps.
Said Brown: “We believed it was simply down to natural pulsation, but as well going to site, we also brought over our top engineers from Germany. It didn’t help us or 2OC that due to the space limitations, the pipework for one pump was straight, whilst the other one was more complex, so had to cope with some pressure loss.”
Tests in Germany with 2OC in attendance showedthat the pumps were performing well, with the vibration due to extra torque being required. Another 500 hours running time, an inspection confirmed that there were no issues.
2OC’s Phil Jones added: “Through the very positive dialogue between the two companies, it was also decided to change the pump’s removable rotor tips from rubber to a fully stainless-steel solid rotor design because of the high temperatures. Together with the stainless-steel pump-head, it now means that there is almost zero maintenance required”.
Phil Jones from 2OC concluded: “Our pursuit of getting this unique power station where it needs to be has not been easy, but very much in line with what government is promoting, we now have a very neat and efficient plant. This includes the Börger pumps, which are proving very efficient, reliable and easy to maintain thus far.”